For the generic disposal design, how many fuel assemblies per canister, and how many canisters fit into the waste disposal section of one borehole?

How Can We Help?

For the generic disposal design, how many fuel assemblies per canister, and how many canisters fit into the waste disposal section of one borehole?

You are here:
< All Topics

Each canister contains a single spent fuel assembly from a Pressurized Water Reactor (PWR). A 1 km-long disposal section holds about 150 canisters. An array of 10 parallel disposal sections holding a total of 1,500 PWR assemblies would accommodate the waste being produced by a 1,000 MWe nuclear power plant in 30 years.